Thiotte educational project · Southeast Haiti
Budget & Progress
A transparent view of the proposed resources, funding priorities and implementation pathway needed to bring the school to a fully equipped opening.
Preliminary full opening estimate
$746,000
As stated in the proposal; see reconciliation below.
Urgent next-phase requirement
$250,000
Not the total cost of opening the school.
Current request to continue project
$100,000
A funding request to continue the project, not confirmed funding received.
The proposal covers construction, furnishing and preparation for approximately 700 students, with 800 desk/chair units, a 40-station computer laboratory and a 200-person auditorium. All amounts are in US dollars.
The $100,000 current request to continue the project represents 40% of the $250,000 urgent requirement. The remaining $150,000 is to be pursued through other partners; neither figure represents money already raised.
Master budget · Preliminary estimates
Where the budget goes
Expand any category to see the individual allowances from the submission. These are estimates, not expenditure records.
Construction completion$217,000
- Remaining foundation and structural work
- $30,000
- Concrete, columns and beams
- $25,000
- Block/masonry walls
- $22,000
- Roofing structure and roofing materials
- $25,000
- Ceilings
- $10,000
- Flooring
- $15,000
- Interior/exterior plastering
- $10,000
- Doors and windows
- $12,000
- Security gates and metalwork
- $8,000
- Electrical installation
- $12,000
- Plumbing
- $10,000
- Bathrooms/sanitation
- $10,000
- Water storage, pumps and plumbing infrastructure
- $8,000
- Interior and exterior final painting
- $12,000
- Final construction corrections/repairs
- $8,000
800 student desk/chair units$60,000
- 800 complete units × approximately $75 (700 required + 100 replacements)
- $60,000
Classroom furniture$24,500
- Teacher desks
- $4,000
- Teacher chairs
- $2,500
- Classroom storage cabinets
- $5,000
- Bookshelves
- $4,000
- Student activity tables
- $3,000
- Classroom tables
- $3,000
- Additional classroom chairs
- $3,000
Boards and teaching equipment$24,500
- Large classroom whiteboards
- $6,000
- Teacher board accessories
- $2,000
- Bulletin boards
- $1,500
- Maps and educational displays
- $2,000
- Teaching aids
- $3,000
- Mathematics and science materials
- $4,000
- Art supplies
- $2,000
- General classroom supplies
- $4,000
Textbooks and school materials$55,000
- Student textbooks
- $20,000
- Workbooks
- $7,000
- Notebooks
- $5,000
- Pens, pencils, erasers and rulers
- $4,000
- Teacher instructional materials
- $3,000
- Library books
- $7,500
- Educational reference materials
- $3,500
- School-supply reserve
- $5,000
40-computer laboratory$53,250
- 40 student computers
- $24,000
- Keyboards, mice, headsets and accessories
- $2,000
- Computer desks
- $5,000
- Computer chairs
- $4,000
- Teacher computer
- $1,000
- Teacher desk and chair
- $750
- Network switches and cabling
- $3,000
- Wi-Fi/network equipment
- $2,000
- Printer/scanner
- $1,500
- UPS and power protection
- $3,000
- Software/licensing allowance
- $3,000
- Server/storage/backup
- $2,000
- Installation and configuration
- $2,000
200-person auditorium/movie theater$52,750
- Approximately 200 auditorium chairs
- $14,000
- Large projection screen
- $2,500
- High-quality projector
- $4,000
- Backup projection equipment/accessories
- $2,000
- Sound system and speakers
- $5,000
- Amplifier/mixer
- $2,000
- Wireless microphones
- $1,500
- Wired microphones
- $500
- Stage lighting
- $2,500
- Stage curtains
- $2,000
- Podium
- $750
- Stage/platform
- $4,000
- Media computer
- $1,500
- HDMI/cabling/accessories
- $1,000
- Acoustic treatment
- $4,000
- Electrical/power protection
- $2,500
- Installation
- $3,000
Administration/offices$29,500
- Principal’s office furniture
- $3,000
- Administrative desks
- $4,000
- Administrative chairs
- $2,000
- Reception furniture
- $2,000
- Filing cabinets
- $2,000
- Bookshelves/storage
- $2,000
- Office computers
- $4,000
- Printers
- $2,000
- Scanner/copier
- $2,500
- Telephone/communication equipment
- $1,000
- Office supplies
- $2,000
- Staff-room furniture
- $3,000
Library / resource center$20,000
- Books and reference materials
- $7,500
- Shelving
- $4,000
- Tables
- $2,500
- Chairs
- $2,000
- Librarian desk
- $750
- Computer
- $750
- Printer
- $500
- Educational/reference materials
- $2,000
Landscaping$40,000
- Site grading
- $7,500
- Soil/topsoil
- $3,000
- Grass/groundcover
- $3,000
- Trees
- $3,000
- Plants/shrubs
- $2,500
- Walkways
- $5,000
- Landscaping labor
- $5,000
- Drainage
- $5,000
- Outdoor lighting
- $3,000
- School entrance landscaping
- $3,000
Fountain and entrance feature$17,000
- Fountain structure
- $6,000
- Pump
- $1,500
- Water circulation system
- $1,000
- Electrical installation
- $1,000
- Plumbing
- $1,000
- Stone/tile/finish
- $2,500
- Surrounding landscaping
- $2,000
- Installation
- $2,000
Security and safety$21,000
- Security gates
- $5,000
- Exterior lighting
- $4,000
- CCTV/security cameras
- $5,000
- Fire extinguishers
- $2,000
- Emergency equipment
- $1,500
- First-aid equipment
- $1,000
- Security/access system
- $2,500
School-wide technology/connectivity$18,500
- School Wi-Fi infrastructure
- $5,000
- Routers/network switches
- $3,000
- Access points
- $3,000
- Network cabling
- $3,000
- Internet installation
- $1,500
- Backup connectivity
- $1,500
- Administrative networking
- $1,500
Cleaning, maintenance and opening supplies$17,000
- Cleaning equipment
- $3,000
- Trash/recycling containers
- $2,000
- Maintenance tools
- $3,000
- Groundskeeping equipment
- $2,000
- Cleaning supplies
- $2,000
- Basic maintenance inventory
- $3,000
- Opening supplies
- $2,000
Transportation and logistics$28,000
- Construction-material transportation
- $10,000
- Furniture transportation
- $5,000
- Computer/equipment transportation
- $3,000
- School-material transportation
- $3,000
- Loading/unloading/handling
- $3,000
- Procurement/logistics
- $4,000
Engineering, supervision and project management$19,000
- Engineering/technical review
- $5,000
- Construction supervision
- $8,000
- Quantity/material verification
- $3,000
- Financial/project administration
- $3,000
Contingency / price-adjustment reserve$50,000
- Reserve for price changes, transportation, material availability, site conditions, corrections, replacement and essential unforeseen requirements
- $50,000
Final amounts are subject to site measurements, architectural and engineering quantities, written supplier/contractor quotations in Haiti, transportation costs and actual site conditions before procurement.
Implementation & accountability
From construction to opening
Current progress
The submission states that work has begun and is being documented through photographs and video. It does not provide actual expenditure totals or verified completion percentages for these budget categories.
View construction updates, photos & videosProposed implementation schedule
Planning milestones, not completed work. No calendar start date is specified; timing will adjust to funding, site conditions, supplier availability and actual progress.
Week 1Proposed
Mobilization, supplier confirmation, procurement planning and priority purchases.
Week 2Proposed
Construction continuation, material delivery and labor deployment.
Week 3Proposed
Structural/masonry work and continued procurement.
Week 4Proposed
Concrete/structural activities and site progress review.
Weeks 5–8Proposed
Major construction, masonry, roofing and building-completion activities.
Weeks 9–12Proposed
Interior work, electrical, plumbing, flooring, ceilings and finishing.
Weeks 13–16Proposed
Painting, doors, windows, classroom preparation and final construction work.
Weeks 17–20Proposed
Furniture procurement, computer laboratory preparation, auditorium installation, educational-material procurement, landscaping and final setup.
Final stageProposed
Inspection, cleaning, corrections, inventory, equipment installation, staff preparation and school opening.
Planned weekly reporting
The proposal commits to weekly expenditure summaries and construction reports, supported by supplier invoices and receipts, labor and payment records, purchase orders and delivery records, photographs and video, and material/equipment inventories.
Final physical inspection, a final financial report and documentation of how partner funds were applied are also planned. The proposal does not include these completed reports.
Source document · 11 pages
Full project proposal
Laurent Family Foundation — Thiotte Educational Project: Full Project Concept Note, Implementation Plan & Master Budget.